The Industry 4.0 space is progressing nicely with walls up, electrical being installed, and floor preparation set to begin.

Starc wall purchased to divide classrooms. Grounds crew to construct.

Floor epoxy has been completed over the south end of the facility. Drywall, painting, and MEP continue.

MCEC Industry 4.0

Demo existing temp walls
Remove existing equipment
Paint walls
Build classroom space
Electrical Installation
Floor prep and epoxy
Finish classroom space
Install equipment
Walter Shannon
Advanced Mfg Ctr
Carpenter Associates
.
.
.
.
.
.
|

04/03/2025

Consigli
Construction
03/12/2025

The new University of Maine College of Engineering and Computing (MCEC) Student Success Center, Industry 4.0, and other AMC renovations are underway and nearing completion. The project includes renovations on the 2nd floor of AMC to construct the MCEC Student Success Center. Industry 4.0 will be located on the 2nd floor within the lab portion of the facility. This summer, a new staircase will be added from the main lobby to the 2nd floor, allowing easier access to the new Student Success Center and Industry 4.0. Funding of $4.5 million, $1 million from HAF/UMS TRANSFORMS MCEC for the construction of the new staircase and Student Success Center, and $3.5 million in FY23 Congressionally Directed Spending secured by U.S. Rep. Golden with the support of U.S. Sens. Collins and King from the Department of Defense Industrial Base Analysis and Sustainment for construction and equipment for Industry 4.0. The design firm for Student Success and Industry 4.0 is Carpenter Associates, the design firm for the monumental staircase is WBRC, and the construction manager for all three is Consigli Construction with support from the UMaine Facilities Shops.

$500,000

Last Updated:

Dana Underwood

IMG_2105.HEIC
YES
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
.

Construction Photos and Documents 

UmaineDash11A.jpg
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC

Project Documents

Document 1
Document 2
Document 3

Funding Sources and Documents

Document 1
Document 2
Document 3
Document 4
Campus Project Tracker
bottom of page