Current construction budget is approximately 4% over. Value engineering continues. HVAC is largest potential savings by removing some of the redundancy. (SEE SCOPE REDUCTION LIST AT BOTTOM)

Early release package approved. Connecticut to start demo during the week of 06/08/2026. Final GMP dependent on the remaining VE items.

Holding contingency at this point with playground equipment in mind.

Black Bear Academy

Mobilize Site
Connecticut Start
Connecticut Complete
Mass/University Start
University Complete
Massachusetts Complete
Site Complete
Grant Expiration
Logan Doucette
207-401-9458
University Park
Harriman associates
|
.
.
.
.
.
.

06/04/2026

Penobscot G.C.
Construction Drawings
06/08/2026
06/08/2026
08/31/2026
8/17/2026
11/16/2026
12/31/2027
01/31/2027
2030?

SCOPE REDUCTION: Value engineering consists mainly of non-programmatic changes. Items removed from the schematic design scope include new roofing, vinyly siding, and windows, none of which will be possible at this time. Millwork quality has been lowered from original specifications and the amount of earthwork, paving etc. has been reduced. Cubbies are being donated and refurbished as opposed to purchased. Removing certain HVAC redundancies offers a major potential savings to bring project back on budget. These options are currently under review.

 

$4,000,000
1/31/2027

Last Updated:

Dana Underwood

IMG_2105.HEIC
YES
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
.

Construction Photos and Documents 

UmaineDash11A.jpg
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC
IMG_2105.HEIC

Project Documents

Funding Sources and Documents

Document 1
Document 2
Document 3
Document 4
Campus Project Tracker